SCADA & PLC / DCS System Architecture — Practical Design Guide
SCADA & PLC / DCS System Architecture — Practical Design Guide
1. Gather requirements (first and most important)
- Process overview: P&ID, key loops, sequences, interlocks, movement (motors, valves, drives).
- Operational modes: auto, manual, emergency, safety interlocks, recipe handling.
- Number & type of I/O: digital inputs (DI), digital outputs (DO), analog inputs (AI), analog outputs (AO), special I/O (pulse, thermocouple, RTD, HART, high-speed counters).
- Performance targets: scan time/loop response, determinism, jitter limits, throughput.
- Availability & redundancy targets: (e.g., 99.99% uptime).
- Physical constraints: device locations, hazardous areas, distances, indoor/outdoor enclosures.
- Cyber & safety requirements: network segmentation, firewall, access control, SIL/Safety PLCs if required.
- Future growth: spare IO, spare CPU/memory margin, network capacity.
- Project deliverables: FAT/SAT, documentation, O&M manuals, training.
2. Instrument I/O calculation (do this early)
Make a tabular IO list from the P&IDs. For each signal include: tag, type (AI/DI/DO/AO), signal range, loop priority (critical/non-critical), location, cable distance, required sampling rate, protocol (4–20 mA, HART, Modbus, Profibus, Ethernet/IP).
Sum totals per panel/area. Add spares: typical 10–25% spare I/O per module/bay (project dependent).
Identify special modules: RTD/TC cards, high-speed counters, encoder interfaces, pulse outputs, thermowell junction boxes.
3. Choose controller platform: PLC vs DCS vs PC-based
PLC: modular, rugged, good for discrete and batch, lower upfront cost; pick PLC families that support required I/O, communication stacks and third-party device compatibility.
DCS: best for continuous / process plants that need tight control, advanced control strategies, operator management, built-in redundancy, and integrated engineering tools.
Hybrid: PLCs for skid/control panels + DCS for plant-wide loops is common.
Controller selection checklist
- I/O capacity and distribution: local vs remote I/O (I/O racks vs remote I/O over fieldbus/Ethernet).
- CPU performance and memory: ensure enough memory for code, tags, historical buffer, recipes, and margins for growth. For fast loops choose CPUs with high scan-rate performance.
- Redundancy needs: single CPU or dual redundant CPU (PLC pairs or redundant DCS controllers). If required, choose controllers and fieldbus supporting hot-standby.
- I/O redundancy: some DCS offer redundant I/O modules/paths for critical loops. Include for safety-critical or high-availability processes.
- Safety controllers: if safety functions are required, select certified safety PLCs (SIL-rated) and segregate safety I/O.
4. Control strategy & performance tuning
Determine loops requiring fast scan (PID for servo/drive control) vs normal scan. Map loop timing to CPU capabilities.
Decide where to run advanced control (in controller vs higher-level DCS module vs external APC server).
Consider segregating high-speed or high-priority loops to dedicated CPUs or local PLCs to ensure determinism.
5. SCADA / HMI selection
DCS often includes integrated operator station(s). For PLC-based systems choose SCADA/HMI compatible with PLC communication and tag count.
Confirm features: alarm management, historian, trending, recipe management, security, reporting, remote access.
Determine redundancy: single SCADA server or redundant SCADA (hot-standby). For critical operations choose redundant SCADA servers and redundant operator stations (thin/fat clients).
Operator stations: decide direct (dedicated for DCS) or flexible stations (floating licenses) depending on license model and architecture.
6. Communication protocols & media
Protocol choice driven by devices and distance: Modbus RTU (RS485), Modbus TCP / Ethernet, Profibus DP, HART (over 4–20 mA), OPC UA, EtherNet/IP, Profinet.
Media: copper Ethernet (100/1000Base-T), fiber optic (for long runs and EMI immunity), RS485 (shorter runs), wireless (with caution).
For long distances or noisy environments use fiber or add repeaters/amplifiers. Consider media converters for protocol bridging.
Network devices: managed switches with VLANs, industrial firewalls, routers, media converters, PoE requirements for HMIs/IP cameras.
7. Physical architecture & placement
Central control room for main server/SCADA/DCS controllers; local control panels near process areas for skid PLCs and field junctions.
I/O MARSHALLING: decide between on-panel marshalling or remote I/O (Profibus/EtherNet/IP Remote I/O) to reduce cable runs.
Cable routing, conduit, earthing, lightning protection and instrument isolation must be planned.
8. Redundancy & high-availability design
Controller redundancy: dual CPUs in hot-standby. DCS typically supports automatic failover; PLC redundancy varies by vendor.
I/O redundancy: redundant I/O modules or redundant I/O paths for critical loops.
Network redundancy: ring topologies (Media Redundancy Protocol), multi-homing, redundant switches, dual network interfaces on servers.
SCADA redundancy: active/standby servers, mirrored historians (or clustered DB).
9. Power & grounding
UPS for control room and critical equipment, separate instrument power supplies if needed, consider DC power redundancy (dual DC power sources).
Proper earthing and shielding for analog signals, surge protection for long cable runs.
10. Cybersecurity & access control
Network segmentation (DMZs), VLANs for separating enterprise and OT.
Use secure protocols (OPC UA with encryption), disable unused services, enforce strong passwords and role-based access.
Patch management plan and backup/restore of controller and SCADA configurations.
11. Testing, FAT & Commissioning
Factory Acceptance Test (FAT) for controllers and HMI/SCADA.
Integration testing: protocol interoperability, alarm flow, interlocks, historian.
Site Acceptance Test (SAT) and commissioning: loop checks, tuning, safety interlocks verification.
12. Documentation & training
As-built P&IDs, Loop diagrams, I/O list, wiring diagrams, network diagrams, configuration backups.
Operator & maintenance training, runbooks for failover and emergency procedures.
13. Maintenance & lifecycle
Spare parts (I/O modules, CPUs), firmware/software version control, maintenance SLA for network and servers.
Plan for future expansions and take into account EOL of chosen hardware.
Quick Practical Checklist (copy/paste)
- Create detailed I/O spreadsheet (Tag / Type / Location / Cable length / Sampling rate).
- Determine critical loops & required scan time.
- Sum I/O counts and add 10–25% spares.
- Select PLC/DCS family with required CPU, I/O modules, and redundancy features.
- Choose SCADA: check tag capacity, historian, alarm & redundancy.
- Choose communication protocols and media; confirm field device compatibility.
- Design network topology & redundancy (VLANs, redundant switches).
- Specify power, UPS, grounding, surge protection.
- Security: VLANs, firewalls, user roles, secure protocols.
- Plan FAT, SAT, commissioning, and operator training.
Example: How to pick a controller & memory sizing (short)
For each analog/digital tag, estimate how much memory the controller uses (consult vendor: tags + data blocks + alarm blocks + recipe memory).
Estimate program size (function blocks, PID counts). Add 30–50% headroom.
Example rule-of-thumb: small skid PLC (<200 IO) → compact PLC with local I/O; medium plant (200–2000 IO) → modular rack PLC; large continuous plant (>2000 IO) → DCS or large modular PLC with remote I/O.
If redundancy required, pick a vendor/model that supports hot-standby CPUs and mirrored I/O.
Architecture diagram
Field devices → Junction Boxes → Remote I/O racks (or marshalling panel) → Local PLC/Skid controllers → Plant Main PLC/DCS controllers (redundant) → SCADA / Historian / Engineering station → Operator Stations (redundant) → Enterprise network (segregated).
Connect critical loops to redundant network paths and redundant power.